Select Learning Curve from the Employees drop down menu.
Field | Description |
---|---|
Learning Curve Name | Type the name of a learning curve plan which can be alphanumeric and must be unique. |
Facility | Select a facility the learning curve plan will be associated to from the drop down list. |
Selection Criteria | Select which type of criteria the plan will run on from the drop down list: Activity, Activity Group, or Zone |
Activity Group | Select an activity group the plan will run on by clicking . |
Activity Name | Select an activity the plan will run on by clicking . |
Zone Name | Select a zone the plan will run on by clicking . |
Description | Type additional information in the text area. |
Progression Type | Select how the employee will progress through the plan. Currently there is only one option, 'Stepped Progression'. |
Std Time Adj % | Enter a numeric value for the standard time adjustment % (STAP). |
Duration | Enter a numeric value, either in days or weeks, that represents how long the plan will last once an employee has been assigned to the plan. |
Effective Date | Select a date which the plan will become effective by clicking . |
Review Period | Length of time which worked assignments will be reviewed to determine if the employee has progressed. Enter a numeric value, either in days or weeks. |
Min. Exposure Hours | Enter a numeric value, in hours, that represents the minimum amount of hours an employee must work in order to be reviewed. |
Select which selection criteria the plan will focus on from the drop down list.
Select the activity, activity group, or zone you would like the plan to run on by clicking
.Info
Enter the number of minimum hours an employee must be exposed to the specified activity, activity group, or zone.
Select
to create the new learning curve plan.Info
Click on the 'Assign Employees' tab.
Click 'Select Employees' link and a popup window appears.