Table 9. Labor Planning Tabs
Labor Planning Screen Sections:
Tab | Section | Description | |
---|---|---|---|
Plan Info | DescriptionSchedule Plan | Select a date of the earliest schedule in the shift for the Start Time and select the latest schedule in the shift for the End Time. | |
Plan Info | Plan Resource | All the employees who are available for the selected plan are listed in the 'Plan Resource' section. They can also be marked absent for that plan. | |
Plan Info | Data Source | You should select the data source. |
...
Select the option for calculating standard work for the labor plan.
|
...
|
...
|
...
| |||
Plan Recap | Description | Segment Settings | Segments that are configured in Labor Planning Configuration (this is covered in a separate manual covering configuration) screen can be planned in 'Segment Settings' section in Plan Recap tab, the planned segments have a priority and employees are first assigned to a plan segment with highest priority. |
---|---|---|---|
Plan Progress | DescriptionProgress Indicator | The progress of work in a particular plan segment can be viewed in 'Progress Indicator' section of Plan Progress tab. | |
Employees | DescriptionAssigned Employees | Employees assigned to a plan segment by the process depending on the work to be done and the work remaining in that plan segment are listed in this 'Assigned Employees' section of the Employees tab. | |
Employees | Released Employees | Employees released from a plan segment or the employees yet to be assigned by the process depending on the work to be done and the work remaining in that plan segment are listed in this 'Released Employees' section of the Employees tab. |
Table 10. Labor Planning Sections
For Functional Concepts of Labor Planning, Refer Appendix A.