  1. Disable the scheduled task operations in both the Source and Destination environments.
    1. Log in to ProTrack Warehouse.
    2. Click on the System tab under the Configuration menu.
    3. Click on the Scheduled Task sub-tab.

      image
      imageSystem Config.jpg
      titleFig.198 System Configuration


    4. Select "N" for ALL of the drop down boxes.
    5. Select all of the check boxes.

      image
      imageDisable Sys.jpg
      titleFig.198 System Configuration - Disable System


    6. Click to save the changes.
  2. Ensure that all processing in both environments is complete.
    1. Scheduled Request Records.
      1. Click on the Monitor tab.
      2. Click on the Scheduled Request tab.
      3. Click Image Added.
      4. Search for all records where the status is INP.
      5. If there are any records in INP wait for these records to leave INP status. All WMS processing is complete when there are no records in the Scheduled Request that are in INP status.
    2. Batch Process Records.
      1. XYZ data is imported based on a batch process that runs based on a configurable time interval.
      2. Check that there are no files in the import directories on the application server for the following import types:
        1. Facility
        2. Floor
        3. Aisles Path
        4. Segment
        5. Location
        6. Travel Path