  1. Click the Assignment ID link in the 'Assignment Information' section of the Kiosk screen. The Assignment ID field will be automatically populated with the in-progress assignment.
  2. Click . The status of the assignment will be set to In-Progress in the 'Assignment Information' section.

...


Splitting An Assignment

ProTrack ProTrack Warehouse provides the capability to allow two or more associates to be working on the same assignment concurrently. If an Active assignment is linked to an associate and another associate requests to work on the same assignment, ProTrack Warehouse splits the assignment into separate assignments (ProTrack Warehouse will append a dash followed by a sequential number, for example '-1' to the end of the assignment). The split assignments will be linked to each associate. The start time and end time are recorded for each associate independently against their respective assignment.

...

  1. Enter the shared Assignment ID in the Assignment ID field of the 'Perform Assignment' section of the Kiosk screen.
  2. Click in the 'Perform Assignment' section and a new assignment will be generate: the original assignment ID with a "-1" appended to the end.

    image
    imageK Split.jpg
    titleFig.315 Kiosk - Split Assignment


  3. The new assignment ID is shown in the Assignment ID field of 'Current Assignment' section and the status of the assignment is set to INP in the 'Assignment Information' section.

...


Grouping Assignments

To increase efficiency, ProTrack Warehouse provides the capability to allow an employee to perform multiple assignments at once. A user can create a "group" assignment by creating a list of individual assignments and then grouping them all together. The newly-created assignment ID will start with "GRP".

...

  1. Ensure that the employee has the capabilities to Group Assignments in the Kiosk (refer to Work Info).
  2. Click at the bottom of the screen. A popup screen appears.

    image
    imageK Group.jpg
    titleFig.316 Kiosk - Grouping Assignments


  3. Enter an assignment and click .
  4. Repeat until all assignments have been added.

    image
    imageK Multi Group.jpg
    titleFig.317 Kiosk - Grouping Multiple Assignments


    Tip
    titleTip
    • To remove an assignment from the group, click the Delete link next to the assignment.

  5. Click to start the Group Assignment.

    image
    imageK GAss.jpg
    titleFig.318 Kiosk - Grouped Assignments


Creating a "Manual" Standard Assignment at the Kiosk

ProTrack Warehouse enables a warehouse associate to create a standard assignment at the Kiosk, "on-the-fly". An assignment need not exist ahead of time in this scenario.

To create a standard assignment:

  1. Ensure the facility is configured to allow creation of standard assignments through the Kiosk (refer to Facility).
  2. Click on the Standard assignment type radio button.

    image
    imageK Std.jpg
    titleFig.319 Kiosk - Standard Assignment


  3. A popup window appears, listing activities that have been setup for "Manual" assignments.

    image
    imageK Act List.jpg
    titleFig.320 Kiosk - Activity List


  4. Click on the activity ID link for the assignment.
  5. Click Image Added and the KVI Entry screen will appear.

    image
    imageK KVI.jpg
    titleFig.321 Kiosk - KVI Entry


  6. If KVI counts are known ahead of time, click Image Added and enter the counts within the respective fields.
  7. Click Image Added once the counts have been entered or if counts are unknown.
  8. The newly-created assignment will be listed in 'In Progress' status on the Kiosk screen.


Indirect Assignments

To create an Indirect Assignment in Kiosk:

  1. Select the Indirect assignment type radio button in the 'Create Assignment' section of Kiosk screen.

    image
    imageK Ind.jpg
    titleFig.322 Kiosk - Indirect Assignments


  2. A list of indirect activities appears in a popup window.

    image
    imageK Ind List.jpg
    titleFig.323 Kiosk - Indirect Activity List


  3. Click the selected Activity ID link. The Activity ID is updated in the Activity ID field.
  4. Click Image Added in the 'Create Assignment' section of the Kiosk screen. The Indirect Activity will appear in 'Assignment Information' as In Progress.

    image
    imageK Ind INP.jpg
    titleFig.324 Kiosk - Indirect In Progress


    Info
    titleInfo
    • Indirect assignments created through the kiosk will have assignment IDs beginning with "OTH".