  1. Log in to ProTrack Warehouse.
  2. Select Daily Inquiry under the Operations menu. The Daily Inquiry screen appears.


    Fig.1 Daily Inquiry

...

Field

Description

Equation

Total Hours

Total time the Employee worked that day, from SOD to EOD.

 

Time on Standard

Total time the Employee spent on Standard Direct Activities.

 

Adjusted Std. Time Earned

Total time the Employee should spend on Standard Activities with Learning Curve applied.

 

Std Time

Total time the Employee should spend on Standard Activities.

 

Delay Time

Total time spent on Delays.

 

Indirect Time

Total time spent on Indirect Activities.

 

Paid Break

Total time an Employee spent on Paid Break(s).

 

Unpaid Break

Total time an Employee spent on an Unpaid Break.

 

KVI / HLD

Total time in Standard Activities that are currently in KVI or HLD status.

 

Adjusted Performance

The comparison of the Adjusted Standard Time (which includes learning curve,
if applicable) allowed on a specific task to the Actual Time used for that same task.

Baseline Performance

The Comparison of the Standard Time Allowed on a Specific Task or Operation to the
Actual Time used for that Same Task or Operation.

Utilization

The Comparison of Actual Time on Standard to the Total Time Available.

Image RemovedImage Added

Effectiveness

The Comparison of Actual Time on Delays to the Total Time Available.

...