Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Reverted from v. 2

...

  • Editing the start or end times slightly (less than 2 hours) to account for early / late arrivals or departures.
  • Editing the start or end times drastically (typically more than 6 hours) because the employee was not assigned to the correct schedule group.

Editing

...

Select the “Edit Work Hours” button above the work week.

A popup box will appear.

Enter the Start/End times under the “Work Hours” or “Buffer Hours” tab and click +Save

Can now be done with date/time picker

 Image Removed

Enter the Start/End times under the “Work Hours” or “Buffer Hours” tab and click +Save

Can be done in date/time picker

 Image Removed

Options: (Drop Down)

Edit, No Transfer

Transfer Assignments

...

a Schedule's Start or End Time

In the following screenshot, the employee was scheduled to start at 3:00 p.m. but didn't actually start working until 4:00 p.m., so it is necessary to adjust the Schedule Start Time by an hour.

  1. Click on the blue bar with the white hyperlink in the center of the weekly schedule view.

    Image Added

  2. A popup window appears which allows you to edit the schedule, transfer assignments, or split the work schedule.

    Image Added

  3. On the left side, enter the new start time of 4:00 p.m., and click the Save button. The DI refreshes with the new schedule start time of 4:00 p.m.
  4. The same process may be applied for editing a schedule's end time.