The Daily Inquiry in ProTrack Warehouse is a valuable tool for performing validation of work performed; educating employees on engineered standards, ensuring delays are credited to the proper function, and to check employees for performance issues.

The Daily Inquiry screen helps you to see the current performance of an employee. In addition to providing visibility of an employee's workday, this screen provides several additional features for approving, reshuffling, changing, adding or deleting work from the employee's past or present workday.

The following table represents the various statuses an assignment would be seen on the Daily Inquiry.

Abbreviation

Expansion and Description

ADD

Addition – An assignment pending reshuffle.

CAL

Calculating – Standard calculation for an assignment is currently processing.

COM

Completed – An assignment that was completed by an employee and has been fully processed.

ERR

Error – An assignment that was completed by an employee but could not be slotted into the work schedule.

GRP

Group – Multiple pre-downloaded assignments worked simultaneously. ProTrackWarehouse groups them together as a single work assignment.

HLD

Hold – Assignment is placed on hold.

KVI

Key Volume Indicator – An assignment waiting for KVI values to be entered. Example of KVI is number of pallets or number of cases.

Table 2. Daily Inquiry Abbreviations


To access the Daily Inquiry screen:

  1. Select the Daily Inquiry tab under the Operations menu. The Daily Inquiry screen appears.


    Fig.2 Daily Inquiry

Search Employee

To view an employee's details in the Daily Inquiry screen, the employees can be searched for by providing the following search criteria in the Search Daily Inquiry screen:

  • Schedule Date – Past date or current date
  • First Name
  • Last Name
  • Facility Name

To search for an employee:

  1. Click to search an employee, the Search Daily Inquiry screen appears.


    Fig.3 Daily Inquiry - Initial Search


  2. Type or select search criteria as required. Criteria fields are Schedule Date, First Name, Last Name, or Facility.

    Tips

    • To list the employees with First Name or Last Name starting with a particular character, type the character and the employees starting with the given character are displayed in the 'Search Results' list.
    • Click and select Schedule Date to list the employees for the selected schedule date. Click Search in the Search Daily Inquiry screen. The records matching the selected criteria are listed in the 'Search Results' section of the Search Daily Inquiry screen.

  3. Click in the Search Daily Inquiry screen. The records matching the selected criteria are listed in the "Search Results" section of the Search Daily Inquiry.


    Fig.4 Daily Inquiry - Search


  4. You can also filter your search results by selecting any of the column header links.

  5. Click the selected employee ID link. The weekly view, schedule, and assignment details of employee will be displayed.


    Fig.5 Daily Inquiry - Detailed View of an Employee's Daily Activity


    At the top of the screen resides a graphical view of the employee's weekly schedule. The current day being viewed is always in the center, with 2 days prior on the left, and 2 days following on the right.

    Tip

    The centered date matches the "Schedule Date" in the center section below.

The yellow and dark blue bars illustrate the employee's schedules on each day. The yellow bar represents the schedule the employee was assigned to work. The blue bar represents the actual schedules the employee worked. Only days containing actual work schedules will have a blue bar. In the screenshot above, you can see that the employee was assigned to a schedule all 5 days (Saturday through Wednesday), but did not work on Sunday.

Also contained within the bars are the Schedule start and end times:


Fig.6 Daily Inquiry – Weekly View – Schedule Start and End Times Within the Graphs

The date currently being viewed has a hyperlink. Clicking on this enables you to edit the Schedule's start and end times manually. This is useful when the employee did not work the schedule to which they were assigned.


Daily Inquiry Header Field Description

Field

Description

Total Hours

Total time the Employee worked that day, from SOD to EOD

Time on Standard

Total time the Employee spent on Standard Activities

Adjusted Std. Time Earned

Total time the Employee should spend on Standard Activities with Learning Curve applied.

Std Time

Total time the Employee should spend on Standard Activities

Delay Time

Total time spent on Delays.

Indirect Time

Total time spent on Indirect Activities

Paid Break

Total time an Employee spends on Paid Break

Unpaid Break

Total time an Employee spend on an Unpaid Break

KVI / HLD

Total time in Standard Activities that are currently in KVI or HLD status

Adjusted Performance

The comparison of the Standard Time allowed on a specific task to the Actual Time used for that same task.
is Adjusted Std. Time Earned divided by Time on Standard minus 1.

Baseline Performance

The Comparison of the Standard Time Allowed on a Specific Task or Operation to the Actual Time Used for that Same Task or Operation
is Std Time divided by Time on Standard minus 1.

Utilization

The Comparison of Actual Time on Standard to the Total Time Available. Is Time on Standard divided by (Total time – Break – Lunch). Shows how much time of your day was spend on Standard Activities

Effectiveness

The Comparison of Actual Time on Delays to the Total Time Available. is Time on Standard plus Indirect divided by (Total time – Break – Lunch).