[!ProTrack Warehouse Wiki^homepage-button_GRN_V3.png!]
Documentation for ProTrack Warehouse 2013 Q4.
When the Manufacturing Module is enable the Production Kiosk will display. The Kiosk can be used to work standard assignments from three different sources:
Predownloads are WMS work assignments that are imported into ProTrack Warehouse. Predownloads are different in that the assignments do not have a start date, start time, end date and end time. There is also no Employee Id because no one has performed the assignment yet.
To access the Kiosk screen:
Select Production under the Kiosk menu. The Production screen appears.
Fig.1 Production Kiosk
Field | Description |
---|---|
Standard Activity | Allows the employee to create a standard direct assignment through the kiosk. |
Indirect Activity | Allows the employee to create an indirect assignment through the kiosk. |
Delay | Allows the employee to add delays they encountered to their day. |
Reset | Clears the kiosk and logs off the employee. |
End All | Ends all assignments that are in progress and on hold. |
To start an assignment:
Enter your employee ID. If authentication is enabled, a popup window will appear asking for your ProTrack password (refer to Employee for kiosk authentication).
Navigate the cursor out of the Work Order field by clicking Tab
The user has the ability to create a new work order through the kiosk, if this is the case a window will popup where the user will enter information concerning the new work order
Fig.3 Production Kiosk - Work Order
Enter the activity or assignment id in the Activity/Assignment ID field.
Navigate the cursor out of the Activity/Assignment ID field by clicking Tab to begin the assignment.
Fig.4 Production Kiosk - In Progress
Info
If the standard time for the entered assignment has not yet been calculated (due to the assignment being recently imported), ProTrack will calculate the standard time “on-the-fly” and then display this standard time on the screen once it’s calculated. Typically this process only takes a few seconds, but may sometimes take longer. In either case, a “Not Yet Available” message will be displayed to the user; the user may either choose to wait for the time to be displayed, or can simply logoff before this process is completed.
Fig.5 Kiosk - Standard Not Yet Available
An assignment is ended from the Kiosk screen. An assignment can either be explicitly ended, or indirectly ended by starting a new assignment.
To end an assignment:
Click either the End All or End button.
Fig.6 Production Kiosk - End Assignment
Info
To put an assignment on-hold:
Click the Hold button to the left of the assignment that will be put on hold.
Fig.7 Production Kiosk - Holding Assignment
The status of the assignment will be set to On-Hold.
Fig.8 Production Kiosk - Holding An Assignment
Info
To resume an assignment:
ProTrack Warehouse provides the capability to allow two or more associates to be working on the same assignment concurrently. If an Active assignment is linked to an associate and another associate requests to work on the same assignment, ProTrack Warehouse splits the assignment into separate assignments. The split assignments will be linked to each associate. The start time and end time are recorded for each associate independently against their respective assignment.
To split an assignment:
Navigate the cursor out of the Activity/Assignment ID field and a new assignment will be generated: the original assignment ID with a "-2" appended to the end.
Fig.8 Production Kiosk - Split Assignment
Info
ProTrack Warehouse enables a warehouse associate to create a standard assignment at the Kiosk, "on-the-fly". An assignment need not exist ahead of time in this scenario.
To create a standard assignment:
Click on the Standard Activity button.
A drop down list appears, listing activities that have been setup for "Manual" assignments.
Fig.9 Production Kiosk - Standard Assignment
If Pre KVI Entry is enabled for the activity, a popup window will appear where the employee can enter in the KVI counts if they are known ahead of time (refer to Activity to enable Pre KVI Entry).
Fig.10 Production Kiosk - KVI Entry
To create an Indirect Assignment in Kiosk:
Select the Indirect Activity button.
A drop down list of indirect activities appears.
Fig.12 Production Kiosk - Indirect Assignments
Select the Activity ID from the drop down list and the assignment will be automatically started.
Fig.13 Production Kiosk - Indirect In Progress
Info
Employees can add delays in their day through the Kiosk. Delays that require supervisor approval will not be applied to the employee's day until the delay has been approved.
To add a delay:
To add a delay to another assignment, click to the left of the assignment ID and the delay drop down list appears.
Info
ProTrack Warehouse will automatically log off the employee once the timer has reached 0 seconds.
Info
To manually Logout of the kiosk:
Click Reset from the Kiosk screen.
Fig.16 Logging Out