On each day, an employee in ProTrack Warehouse is assigned to a schedule. Schedules are used for the following purposes:

Field Description

Field

Description

Schedule Name

Specify a unique Schedule Name, which is alphanumeric. (Combination of Alphabets and Numbers)

Facility ID

The Facility ID this schedule is associated with (could be "all").

Clock-In Time

Start time for a schedule

Duration of SOD

The duration length of the SOD.

Break/Lunch Start Time

Start time of this specific Schedule Activity.

Break/Lunch Duration

The duration length of the Schedule Activity.

Clock-Out Time

End time of the schedule.

Buffer

Enter the buffer duration to allow for assignments outside of the schedule start and end times to be processed. Buffers cannot exceed 24-hours.


  1. To facilitate when an employee's work day starts and ends
  2. To automatically create lunch, breaks and other scheduled activities
  3. To create reporting breakpoints in the time continuum as an employee works throughout a week.

Accessing the Maintain Schedule Screen
The options in the Maintain Schedule screen are available depending on the user privileges. The Maintain Schedule screen helps you to add, search, view, delete, compare, and print schedules in the system.

  1. To access the Maintain Schedule screen, select Schedules under the Employee menu.



Maintain Schedule
Add Schedules
You can add a schedule(s) to an employee using the Maintain Schedule screen.

Maintain Schedule - Add Schedule

    1. Type the Schedule Name. This cannot be changed once the Schedule is saved, so it is recommended you use a descriptive name that will not change over time.
    2. Select the Facility for which the Schedule will be used.
    3. Set the Effective Date and Expiration Date of the Schedule.
    4. Enter the Start and End Times of the schedule.




    1. Scheduled activities are activities which occur every work day (such as lunches and breaks). To add scheduled activities, click Select Activity link. Select an activity from the popup window.
    2. Select the Activity Type from the drop-down list. For breaks select the blank, or for Start or End of Shift select those items accordingly.



    1. Type the Start Time and Duration for each activity.



    1. Scheduled activities may be "TA-Sourced", meaning their times may be adjusted by a Time & Attendance import file. Check the checkbox for any scheduled activities which may be adjusted by a TA import file. Breaks, Lunches, Start of Shift, and End of Shifts may all be TA-sourced. See Section 5.2 for details on configuring Time & Attendance import files.
    2. Click Save to save the schedule.





Field

Description

Schedule Name

Specify a unique Schedule Name, which is alphanumeric. (Combination of Alphabets and Numbers)

Effective Date

Select a date when the schedule has to be active which should be earlier than the expiration date. The default value is the next day's Date.

Expiration Date

Select a date when a schedule expires

Start Time

Enter the start time for a schedule

End Time

Enter the end time for a schedule

Facility

Select a facility name. Default value is All

Schedule Date

Start Date is the only choice.