Documentation for ProTrackWarehouse 2019.1.
Field | Description |
---|---|
Standard Activity | Allows the user to create a standard direct assignment through the kiosk. |
Indirect Activity | Allows the user to create an indirect assignment through the kiosk. |
Delay | Allows the user to add delays that have been encountered in their day. |
Group | Allows the user to group multiple assignments together into one assignment. |
Reset | Clears the kiosk and logs off the user. |
End All | Ends all assignment(s) that are in progress and on-hold. |
There are three different types of standard direct assignments that can be worked using the kiosk.
To begin a PRE assignment:
Tab]
to begin the assignment.
To begin an OPS assignment:
Tab]
to begin the assignment.
To begin a MANUAL assignment:
The user has the ability to put an assignment on hold through the kiosk if they need to work on another assignment or indirect activity. Then once that assignment or indirect activity has been completed, they can pick up the previous assignment, which is on hold, and complete it.
To put an assignment on-hold:
The status of the assignment will change from In-Progress to On-Hold.
To resume an assignment:
There are two ways an assignment can be ended from the kiosk: ending it directly or starting a new assignment. The majority of the time, the user will end the previous assignment by starting another assignment. Typically, the only time the user will directly end an assignment would be at the end of their work schedule because there will be no more assignments to work.
To directly end an assignment:
Click either the End All or End button.
If Enter Post KVI is enabled for the selected activity, the user has the option of entering in the counts (cases, pallets, etc) after the assignment has been ended.
The user has the ability to group multiple assignments of the same activity together. By doing so, it will reduce travel to and from the kiosk and let them focus on the task at hand. To use this feature, it needs to be enabled on the Employee screen before the employee logs into the kiosk.
Group assignments are slightly different than a standalone assignment.
To group assignments together:
Repeat step 3 until all assignments have been added.
Click the Start button and the group assignment will begin.
ProTrack has the capability to have two or more employees working the same assignment concurrently. If an assignment is in-progress by one employee and another employee signs into the same assignment, then ProTrack will split the assignment into separate entities (known as split assignments). The start and end times are recorded for each employee independently towards their respective parts of the assignment.
To split an assignment:
The second user logs out of the kiosk.
Repeat these steps for all employees working the same assignment.
It is recommended that all indirect activities within the facility be tracked to fully understand where hours are going in the facility.The kiosk is an easy way to capture individuals that are on indirect tasks from day to day (i.e. clerks, maintenance, janitors, etc) or if an employee on the floor switches to an indirect task.
To start an indirect activity from the kiosk:
An assignment will be generated and started for the user.
Employees have the ability to add delays that they encounter in their day through the kiosk in lieu of delay sheets or lack of RF interfacing. They can add the delay to the most recent assignment, the first assignment of the day, or any assignment in between. This feature gives the user the flexibility to apply a delay anytime during their day.
To add a delay:
Click the Save button to apply the delay to the selected assignment.
When the timer reaches 0 seconds, the user will be automatically logged off the kiosk. If the user does not want to wait for the timer, then they can click the Reset button to log out of the kiosk.